plan-release-cycle

Plan a software release cycle with milestones, feature freezes, release candidates, and go/no-go criteria. Covers calendar-based and feature-based release strategies. Use when starting planning for a major or minor version release, transitioning from ad-hoc to structured release cadence, coordinating a release across multiple teams or components, defining quality gates for a regulated project, or planning the first public release (v1.0.0) of a project.

Safety Notice

This listing is imported from skills.sh public index metadata. Review upstream SKILL.md and repository scripts before running.

Copy this and send it to your AI assistant to learn

Install skill "plan-release-cycle" with this command: npx skills add pjt222/development-guides/pjt222-development-guides-plan-release-cycle

Plan Release Cycle

Plan a structured software release cycle by defining strategy (calendar-based or feature-based), setting milestones with target dates, establishing feature freeze criteria, managing release candidates, defining go/no-go checklists, and documenting rollback plans. Produces a RELEASE-PLAN.md artifact that guides the team from development through release.

When to Use

  • Starting planning for a major or minor version release
  • Transitioning from ad-hoc releases to a structured release cadence
  • Coordinating a release across multiple teams or components
  • Defining quality gates and release criteria for a regulated project
  • Planning the first public release (v1.0.0) of a project

Inputs

  • Required: Target version number (e.g., v2.0.0)
  • Required: Desired release date or release window
  • Required: List of planned features or scope (backlog, roadmap, or description)
  • Optional: Team size and availability
  • Optional: Release strategy preference (calendar-based or feature-based)
  • Optional: Regulatory or compliance requirements affecting release
  • Optional: Previous release velocity or cycle duration data

Procedure

Step 1: Determine Release Strategy

Choose between two primary strategies:

Calendar-based (time-boxed):

  • Release on a fixed schedule (e.g., every 4 weeks, quarterly)
  • Features that are not ready are deferred to the next release
  • Predictable for users and downstream projects
  • Best for: libraries, frameworks, tools with external consumers

Feature-based (scope-driven):

  • Release when a defined set of features is complete
  • Date adjusts to accommodate scope
  • Risk of scope creep and indefinite delays
  • Best for: internal tools, first releases, major rewrites

For most projects, a hybrid approach works well: set a target date with a defined scope, but allow a 1-2 week buffer. If scope is not met by the buffer deadline, defer remaining features.

Document the strategy choice with rationale.

Expected: Release strategy documented with rationale matching project context.

On failure: If the team cannot agree on a strategy, default to calendar-based with a feature-priority list. Time-boxing forces prioritization decisions.

Step 2: Define Milestones

Break the release cycle into phases with target dates:

## Release Plan: v2.0.0

### Timeline

| Phase | Start | End | Duration | Description |
|---|---|---|---|---|
| Development | 2026-02-17 | 2026-03-14 | 4 weeks | Active feature development |
| Feature Freeze | 2026-03-15 | 2026-03-15 | 1 day | No new features merged after this date |
| Stabilization | 2026-03-15 | 2026-03-21 | 1 week | Bug fixes, documentation, testing only |
| RC1 | 2026-03-22 | 2026-03-22 | 1 day | First release candidate tagged |
| RC Testing | 2026-03-22 | 2026-03-28 | 1 week | Community/team testing of RC |
| RC2 (if needed) | 2026-03-29 | 2026-03-29 | 1 day | Second RC if critical issues found |
| Go/No-Go | 2026-03-31 | 2026-03-31 | 1 day | Final decision meeting |
| Release | 2026-04-01 | 2026-04-01 | 1 day | Tag, publish, announce |

Typical phase durations:

  • Development: 50-70% of total cycle
  • Stabilization: 15-25% of total cycle
  • RC testing: 10-20% of total cycle

Expected: Milestone table with dates, durations, and descriptions for each phase.

On failure: If the timeline is too compressed (stabilization < 1 week), either extend the release date or reduce scope. Never skip stabilization.

Step 3: Set Feature Freeze Criteria

Define what "feature freeze" means for this release:

### Feature Freeze Criteria

After feature freeze (2026-03-15):
- **Allowed**: Bug fixes, test additions, documentation updates, dependency security patches
- **Not allowed**: New features, API changes, refactoring, dependency upgrades (non-security)
- **Exception process**: Feature freeze exceptions require written justification and approval from [release owner]

### Feature Priority List
| Priority | Feature | Status | Owner | Notes |
|---|---|---|---|---|
| P0 (must) | New export format | In progress | [Name] | Blocks release |
| P0 (must) | Security audit fixes | Not started | [Name] | Compliance requirement |
| P1 (should) | Performance optimization | In progress | [Name] | Defer if not ready |
| P2 (nice) | Dark mode support | Not started | [Name] | Defer to v2.1.0 if needed |

P0 features block the release. P1 features should be included if ready. P2 features are deferred without delay.

Expected: Feature freeze rules documented with exception process and prioritized feature list.

On failure: If P0 features are at risk of missing the freeze date, escalate immediately. Options: extend development phase, split the feature into a smaller deliverable, or defer to a point release (v2.0.1).

Step 4: Plan Release Candidate Process

Define how release candidates are produced and tested:

### Release Candidate Process

1. **RC1 Tag**: Tag from the stabilization branch after all P0 features merged and CI green
   ```bash
   git tag -a v2.0.0-rc.1 -m "Release candidate 1 for v2.0.0"
  1. RC Distribution: Publish RC to staging/testing channel

    • R: install.packages("pkg", repos = "https://staging.r-universe.dev/user")
    • Node.js: npm install pkg@next
    • Internal: Deploy to staging environment
  2. RC Testing Period: 5-7 business days

    • Run full test suite including integration tests
    • Verify all P0 features work as documented
    • Test upgrade path from previous version
    • Check for regressions in existing functionality
  3. RC Evaluation:

    • No critical/high bugs: Proceed to release
    • Critical bugs found: Fix, tag RC2, restart testing period
    • More than 2 RCs needed: Revisit scope and timeline
  4. RC2+ Tags: Only if critical issues found in previous RC

    git tag -a v2.0.0-rc.2 -m "Release candidate 2 for v2.0.0"
    

**Expected:** RC process documented with tagging convention, distribution method, testing checklist, and escalation criteria.

**On failure:** If the RC process is skipped (pressure to release), document the risk. Untested releases have higher rollback probability.

### Step 5: Define Go/No-Go Checklist

Create the criteria that must be met before release approval:

```markdown
### Go/No-Go Checklist

#### Must Pass (release blocked if any fail)
- [ ] All CI checks passing on release branch
- [ ] Zero critical bugs open against this version
- [ ] Zero high-severity security vulnerabilities
- [ ] All P0 features verified and documented
- [ ] Changelog complete and reviewed
- [ ] Upgrade path tested from previous version (v1.x -> v2.0.0)
- [ ] License and attribution files up to date

#### Should Pass (release proceeds with documented risk)
- [ ] Zero high bugs open (non-critical)
- [ ] All P1 features included
- [ ] Performance benchmarks within acceptable range
- [ ] Documentation reviewed and spell-checked
- [ ] External dependencies at latest stable versions

#### Decision
- **Go**: All "Must Pass" items checked, majority of "Should Pass" items checked
- **No-Go**: Any "Must Pass" item unchecked
- **Conditional Go**: All "Must Pass" checked, significant "Should Pass" items unchecked — document accepted risks

Expected: Go/no-go checklist with clear pass/fail criteria and decision rules.

On failure: If the go/no-go meeting results in no-go, identify the blocking items, assign owners, set a new target date (typically 1-2 weeks later), and update the release plan.

Step 6: Document Rollback Plan

Define how to roll back if the release causes critical issues in production:

### Rollback Plan

#### Rollback Triggers
- Critical bug affecting >10% of users
- Data corruption or loss
- Security vulnerability introduced by the release
- Breaking change not documented in changelog

#### Rollback Procedure
1. **Revert package registry**: Unpublish or yank the release
   - R/CRAN: Contact CRAN maintainers (cannot self-unpublish)
   - npm: `npm unpublish pkg@2.0.0` (within 72 hours)
   - GitHub: Mark release as pre-release, publish point fix

2. **Communicate**: Notify users via GitHub issue, mailing list, or social channels
   - Template: "v2.0.0 has been rolled back due to [issue]. Please use v1.x.y until a fix is released."

3. **Fix forward**: Prefer a v2.0.1 patch release over a full rollback when possible

4. **Post-mortem**: Conduct a post-mortem within 48 hours of rollback to identify process gaps

#### Point Release Policy
- v2.0.1 for critical bug fixes within 1 week of release
- v2.0.2 for additional fixes within 2 weeks
- Patch releases do not require full RC cycle but must pass CI and critical test suite

Write the complete release plan to RELEASE-PLAN.md or RELEASE-PLAN-v2.0.0.md.

Expected: Rollback plan documented with triggers, procedure, communication template, and point release policy. Complete RELEASE-PLAN.md written.

On failure: If rollback is not feasible (e.g., database migration already applied), document the forward-fix procedure instead. Every release should have a recovery path.

Validation

  • Release strategy (calendar/feature/hybrid) documented with rationale
  • Milestone table includes all phases with dates: development, freeze, stabilization, RC, release
  • Feature freeze criteria defined with allowed/disallowed change types
  • Feature priority list categorized (P0 must / P1 should / P2 nice)
  • RC process documented: tagging convention, distribution, testing period, escalation
  • Go/no-go checklist has clear "must pass" and "should pass" sections
  • Rollback plan includes triggers, procedure, and communication template
  • RELEASE-PLAN.md (or equivalent) file created and saved
  • Timeline is realistic (stabilization is at least 15% of total cycle)

Common Pitfalls

  • No stabilization phase: Going directly from development to release. Even a 3-day stabilization period catches issues that active development masks.
  • Scope creep after freeze: Allowing "just one more feature" after feature freeze. Every post-freeze addition resets testing and introduces regression risk.
  • Ignoring P0 risks: Not escalating early when a P0 feature is at risk. The earlier scope is adjusted, the less disruption to the timeline.
  • Skipping RC for "small" releases: Even minor releases benefit from at least one RC. A day of RC testing is cheaper than a post-release hotfix.
  • No rollback plan: Assuming the release will succeed. Every release plan should answer "what if this goes wrong?" before publishing.
  • Calendar pressure overriding quality: Releasing on a date because it was promised, despite failing go/no-go criteria. A delayed release is a minor inconvenience; a broken release is a trust violation.

Related Skills

  • apply-semantic-versioning -- Determine the version number for the planned release
  • manage-changelog -- Maintain the changelog that feeds into release notes
  • plan-sprint -- Sprint planning within the development phase of the release cycle
  • draft-project-charter -- Project charter may define the release roadmap and success criteria
  • generate-status-report -- Track progress against release milestones

Source Transparency

This detail page is rendered from real SKILL.md content. Trust labels are metadata-based hints, not a safety guarantee.

Related Skills

Related by shared tags or category signals.

Web3

define-slo-sli-sla

No summary provided by upstream source.

Repository SourceNeeds Review
Coding

review-ux-ui

No summary provided by upstream source.

Repository SourceNeeds Review
Coding

review-web-design

No summary provided by upstream source.

Repository SourceNeeds Review