Dependency Mapping Skill

Systematic identification and management of cross-project dependencies.

Purpose

This skill provides a framework for:

  • Dependency identification

  • Dependency classification

  • Impact analysis

  • Critical path identification

  • Dependency tracking and management

Prerequisites

Before dependency mapping, ensure:

Prerequisite Required For Source

Project schedules Timeline analysis Project managers

Project deliverables Dependency identification Project plans

External contracts Vendor dependencies Procurement

Integration points Technical dependencies Architecture

Dependency Types

Internal Dependencies

Type Definition Example

Finish-to-Start (FS) B starts when A finishes Development → Testing

Start-to-Start (SS) B starts when A starts Parallel workstreams

Finish-to-Finish (FF) B finishes when A finishes Code freeze → Doc freeze

Start-to-Finish (SF) B finishes when A starts Rare, shift handoff

External Dependencies

Type Definition Risk Level

Vendor Third-party delivery Medium-High

Regulatory Approval or certification High

Infrastructure Environment availability Medium

Integration API or system availability Medium-High

Resource Shared resource availability Medium

Dependency Mapping Gates

Gate 1: Dependency Identification

Objective: Identify all dependencies across portfolio

Actions:

  • Review project schedules for cross-project links

  • Interview project managers

  • Document deliverable handoffs

  • Identify external dependencies

Identification Questions:

  • What does this project need from other projects?

  • What does this project provide to other projects?

  • What external inputs are needed?

  • What must be complete before this can start?

Output: docs/pmo/{date}/dependency-inventory.md

Gate 2: Dependency Classification

Objective: Classify dependencies by type and criticality

Actions:

  • Classify by dependency type (FS, SS, FF, SF)

  • Classify by source (internal/external)

  • Assess criticality (critical path/slack)

  • Document constraints and assumptions

Criticality Assessment:

Level Criteria Management

Critical On critical path, no slack Daily monitoring

High < 1 week slack Weekly monitoring

Medium 1-4 weeks slack Bi-weekly monitoring

Low

4 weeks slack Monthly monitoring

Output: docs/pmo/{date}/dependency-classification.md

Gate 3: Impact Analysis

Objective: Understand impact of dependency failure

Actions:

  • Analyze schedule impact

  • Analyze cost impact

  • Identify cascade effects

  • Document mitigation options

Impact Assessment Template:

Dependency If Delayed By Schedule Impact Cost Impact Cascade To

[Dep] 1 week [Impact] [Impact] [Projects]

[Dep] 2 weeks [Impact] [Impact] [Projects]

[Dep] 1 month [Impact] [Impact] [Projects]

Output: docs/pmo/{date}/dependency-impact.md

Gate 4: Critical Path Analysis

Objective: Identify and protect the critical path

Actions:

  • Map critical path across projects

  • Identify dependencies on critical path

  • Analyze buffer/slack

  • Recommend protection measures

Critical Path Visualization:

Project A: [Task A1] → [Task A2] → [Deliverable A] ↓ Project B: [Task B1] → [Task B2] → [Deliverable B] ↓ Project C: [Task C1] → [Task C2] → [Final]

Protection Measures:

  • Buffer allocation

  • Parallel path development

  • Early warning triggers

  • Contingency plans

Output: docs/pmo/{date}/critical-path-analysis.md

Gate 5: Dependency Tracking Plan

Objective: Create ongoing tracking and management plan

Actions:

  • Define tracking frequency per criticality

  • Assign dependency owners

  • Create communication plan

  • Define escalation triggers

Tracking Template:

Dependency Owner Update Freq Status Next Milestone Risk

[Dep] [Owner] [Freq] [Status] [Date: Milestone] [Risk]

Escalation Triggers:

  • Critical dependency at risk

  • External dependency delayed

  • Cascade impact identified

  • Owner not responding

Output: docs/pmo/{date}/dependency-tracking-plan.md

Anti-Rationalization Table

See shared-patterns/anti-rationalization.md for universal anti-rationalizations.

Dependency-Specific Anti-Rationalizations

Rationalization Why It's WRONG Required Action

"We've documented the main dependencies" Undocumented dependencies cause surprise delays. Document ALL dependencies

"That's a soft dependency, not critical" Soft dependencies become hard when they fail. Classify and track all

"External vendor always delivers" Past performance ≠ future guarantee. Track and verify externals

"Projects will coordinate directly" Ad-hoc coordination fails under pressure. Formal tracking required

Pressure Resistance

See shared-patterns/pressure-resistance.md for universal pressure scenarios.

Dependency-Specific Pressures

Pressure Type Request Agent Response

"We trust the other team, don't track" "Trust doesn't prevent delays. Tracking enables early action."

"Too many dependencies to track" "Complexity requires MORE tracking, not less. Will prioritize by criticality."

"Vendor said it's on track" "Vendor assurance needs verification. Confirming with evidence."

Blocker Criteria - STOP and Report

ALWAYS pause and report blocker for:

Situation Required Action

Critical dependency at risk STOP. Immediate escalation. Cascade impact pending.

Circular dependency identified STOP. Architectural issue requires resolution.

External dependency failed STOP. Contingency activation required.

Dependency owner unresponsive STOP. Escalate for owner assignment.

Cannot Be Overridden

The following requirements are NON-NEGOTIABLE:

Requirement Cannot Override Because

Complete dependency inventory Hidden dependencies cause surprise delays

Owner assignment Unowned dependencies are unmanaged

External verification Vendor assurance without evidence is unreliable

Critical path protection Critical path delays affect entire portfolio

Cascade impact documentation Unknown cascades become crisis

If user insists on violating these:

  • Escalate to orchestrator

  • Do NOT proceed with incomplete mapping

  • Document the request and your refusal

Severity Calibration

When assessing dependency risks:

Severity Criteria Examples

CRITICAL On critical path, no slack, high impact Core API dependency blocking 3+ projects, vendor at risk of bankruptcy

HIGH < 1 week slack, significant impact Integration dependency with tight timeline, key resource dependency

MEDIUM 1-4 weeks slack, moderate impact Supporting service dependency, documentation dependency

LOW

4 weeks slack, minor impact Nice-to-have integration, optional feature dependency

Track all severities. Actively manage CRITICAL and HIGH.

Output Format

Dependency Map Summary

Cross-Project Dependency Map - [Date]

Dependency Overview

MetricValue
Total DependenciesN
InternalN
ExternalN
On Critical PathN
At RiskN

Dependency Matrix

From ProjectTo ProjectDependencyTypeCriticalityStatus
[Project][Project][Description][FS/SS/FF/SF][Crit/High/Med/Low][On Track/At Risk/Blocked]

Critical Path Dependencies

[Visual representation of critical path]

External Dependencies

Vendor/SourceDependencyDue DateStatusContingency
[Vendor][Dependency][Date][Status][Plan]

At-Risk Dependencies

DependencyRiskImpactMitigation
[Dep][Risk description][Impact][Mitigation]

Recommendations

  1. [Recommendation with rationale]
  2. [Recommendation with rationale]

Decisions Required

  1. [Decision needed with options]

Execution Report

Base metrics per shared-patterns/execution-report.md:

Metric Value

Analysis Date YYYY-MM-DD

Scope [Portfolio/Projects]

Duration Xh Ym

Result COMPLETE/PARTIAL/BLOCKED

Dependency-Specific Details

Metric Value

dependencies_total N

critical_path_deps N

external_deps N

at_risk_deps N

When Dependency Mapping Is Not Needed

Condition Verification

Single isolated project Verify no cross-project dependencies

No external dependencies Confirm all resources internal

No shared resources Verify team is dedicated

Previous mapping is current (<30 days) Reference existing map

MUST: Full dependency mapping REQUIRED for the following conditions:

Condition Why Required

Multiple projects share resources Resource conflicts cause delays

External vendor dependencies exist Vendor delays cascade to projects

Integration points between projects Technical dependencies create coupling

New project added to portfolio Impact on existing dependencies unknown

Critical milestone approaching Risk assessment needs current dependencies

MUST: When in doubt, update the dependency map. Stale dependency information causes crisis.

Source Transparency

This detail page is rendered from real SKILL.md content. Trust labels are metadata-based hints, not a safety guarantee.

Related Skills

Related by shared tags or category signals.

General

ring:regulatory-templates-gate2

No summary provided by upstream source.

Repository SourceNeeds Review
General

ring:regulatory-templates-gate3

No summary provided by upstream source.

Repository SourceNeeds Review
General

ring:documentation-review

No summary provided by upstream source.

Repository SourceNeeds Review