Compress construction schedules when project deadlines are at risk. Apply crashing (adding resources) and fast-tracking (parallel activities) to accelerate delivery while managing cost and risk.

Safety Notice

This listing is imported from skills.sh public index metadata. Review upstream SKILL.md and repository scripts before running.

Copy this and send it to your AI assistant to learn

Install skill "schedule-compression" with this command: npx skills add datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/datadrivenconstruction-ddc-skills-for-ai-agents-in-construction-schedule-compression

Schedule Compression

Overview

Compress construction schedules when project deadlines are at risk. Apply crashing (adding resources) and fast-tracking (parallel activities) to accelerate delivery while managing cost and risk.

"Strategic compression can recover 20% of schedule with 10% cost increase" — DDC Community

Compression Techniques

┌─────────────────────────────────────────────────────────────────┐ │ SCHEDULE COMPRESSION │ ├─────────────────────────────────────────────────────────────────┤ │ │ │ CRASHING FAST-TRACKING │ │ ──────── ───────────── │ │ Add resources to reduce Overlap sequential │ │ activity duration activities │ │ │ │ Before: ████████ (10d) Before: A ──→ B ──→ C │ │ After: █████ (5d) + $$$ After: A ──→ B │ │ └──→ C │ │ Cost: Higher labor/OT Risk: Rework if A changes │ │ │ └─────────────────────────────────────────────────────────────────┘

Technical Implementation

from dataclasses import dataclass, field from typing import List, Dict, Optional, Tuple from enum import Enum

class CompressionMethod(Enum): CRASH = "crash" FAST_TRACK = "fast_track" HYBRID = "hybrid"

@dataclass class Activity: id: str name: str normal_duration: int crash_duration: int # Minimum possible duration normal_cost: float crash_cost: float # Cost at crash duration predecessors: List[str] = field(default_factory=list) is_critical: bool = False current_duration: int = 0

def __post_init__(self):
    if self.current_duration == 0:
        self.current_duration = self.normal_duration

@property
def crash_slope(self) -> float:
    """Cost per day of crashing."""
    duration_diff = self.normal_duration - self.crash_duration
    if duration_diff == 0:
        return float('inf')
    return (self.crash_cost - self.normal_cost) / duration_diff

@property
def days_available_to_crash(self) -> int:
    """Days activity can still be crashed."""
    return self.current_duration - self.crash_duration

@dataclass class FastTrackOption: activity1_id: str activity2_id: str overlap_days: int risk_level: str # low, medium, high risk_description: str rework_probability: float potential_rework_cost: float

@dataclass class CompressionPlan: target_reduction: int achieved_reduction: int crash_activities: List[Tuple[str, int]] # (activity_id, days_crashed) fast_track_options: List[FastTrackOption] total_additional_cost: float new_project_duration: int risk_assessment: str

class ScheduleCompressor: """Compress construction schedules using crashing and fast-tracking."""

def __init__(self):
    self.activities: Dict[str, Activity] = {}
    self.fast_track_options: List[FastTrackOption] = []
    self.project_duration: int = 0
    self.critical_path: List[str] = []

def add_activity(self, id: str, name: str,
                normal_duration: int, crash_duration: int,
                normal_cost: float, crash_cost: float,
                predecessors: List[str] = None,
                is_critical: bool = False) -> Activity:
    """Add activity with crash data."""
    activity = Activity(
        id=id,
        name=name,
        normal_duration=normal_duration,
        crash_duration=crash_duration,
        normal_cost=normal_cost,
        crash_cost=crash_cost,
        predecessors=predecessors or [],
        is_critical=is_critical
    )
    self.activities[id] = activity
    return activity

def add_fast_track_option(self, activity1_id: str, activity2_id: str,
                         overlap_days: int, risk_level: str,
                         risk_description: str,
                         rework_probability: float = 0.1,
                         potential_rework_cost: float = 0) -> FastTrackOption:
    """Add fast-tracking option between activities."""
    option = FastTrackOption(
        activity1_id=activity1_id,
        activity2_id=activity2_id,
        overlap_days=overlap_days,
        risk_level=risk_level,
        risk_description=risk_description,
        rework_probability=rework_probability,
        potential_rework_cost=potential_rework_cost
    )
    self.fast_track_options.append(option)
    return option

def calculate_project_duration(self) -> int:
    """Calculate current project duration using CPM."""
    # Simple forward pass
    finish_times = {}

    def get_finish(act_id: str) -> int:
        if act_id in finish_times:
            return finish_times[act_id]

        act = self.activities[act_id]
        if not act.predecessors:
            start = 0
        else:
            start = max(get_finish(p) for p in act.predecessors)

        finish_times[act_id] = start + act.current_duration
        return finish_times[act_id]

    for act_id in self.activities:
        get_finish(act_id)

    self.project_duration = max(finish_times.values()) if finish_times else 0
    return self.project_duration

def identify_critical_path(self) -> List[str]:
    """Identify critical path activities."""
    # Simplified - in practice, use full CPM
    self.calculate_project_duration()

    # Mark activities with zero float as critical
    critical = [act.id for act in self.activities.values() if act.is_critical]
    self.critical_path = critical
    return critical

def analyze_crash_options(self) -> List[Dict]:
    """Analyze all crashing options sorted by cost efficiency."""
    crash_options = []

    for act in self.activities.values():
        if act.days_available_to_crash > 0 and act.is_critical:
            crash_options.append({
                'activity_id': act.id,
                'activity_name': act.name,
                'crash_slope': act.crash_slope,
                'max_days': act.days_available_to_crash,
                'current_duration': act.current_duration,
                'crash_duration': act.crash_duration
            })

    # Sort by crash slope (cost per day)
    return sorted(crash_options, key=lambda x: x['crash_slope'])

def crash_schedule(self, target_days: int,
                  max_budget: float = float('inf')) -> CompressionPlan:
    """Crash schedule to reduce duration by target days."""
    self.calculate_project_duration()
    original_duration = self.project_duration

    crashed_activities = []
    total_cost = 0
    days_achieved = 0

    # Get crash options
    options = self.analyze_crash_options()

    while days_achieved < target_days and options:
        # Find cheapest option
        best_option = None
        for opt in options:
            if opt['max_days'] > 0:
                best_option = opt
                break

        if not best_option:
            break

        # Crash by 1 day
        act = self.activities[best_option['activity_id']]
        crash_cost = act.crash_slope

        if total_cost + crash_cost > max_budget:
            break

        act.current_duration -= 1
        total_cost += crash_cost
        days_achieved += 1

        # Update option
        best_option['max_days'] -= 1

        # Track what was crashed
        existing = next((c for c in crashed_activities if c[0] == act.id), None)
        if existing:
            crashed_activities.remove(existing)
            crashed_activities.append((act.id, existing[1] + 1))
        else:
            crashed_activities.append((act.id, 1))

        # Refresh options (critical path may change)
        options = self.analyze_crash_options()

    new_duration = self.calculate_project_duration()

    return CompressionPlan(
        target_reduction=target_days,
        achieved_reduction=days_achieved,
        crash_activities=crashed_activities,
        fast_track_options=[],
        total_additional_cost=total_cost,
        new_project_duration=new_duration,
        risk_assessment="Low risk - crashing uses proven methods"
    )

def fast_track_schedule(self, target_days: int,
                       max_risk: str = "medium") -> CompressionPlan:
    """Fast-track schedule by overlapping activities."""
    risk_order = {"low": 1, "medium": 2, "high": 3}
    max_risk_level = risk_order.get(max_risk, 2)

    # Filter options by risk level
    viable_options = [
        opt for opt in self.fast_track_options
        if risk_order.get(opt.risk_level, 3) <= max_risk_level
    ]

    # Sort by overlap (most time saved first)
    viable_options.sort(key=lambda x: -x.overlap_days)

    selected_options = []
    total_overlap = 0
    total_risk_cost = 0

    for opt in viable_options:
        if total_overlap >= target_days:
            break

        selected_options.append(opt)
        total_overlap += opt.overlap_days
        total_risk_cost += opt.rework_probability * opt.potential_rework_cost

    self.calculate_project_duration()
    new_duration = self.project_duration - total_overlap

    risk_text = "High risk" if max_risk == "high" else "Moderate risk" if max_risk == "medium" else "Low risk"

    return CompressionPlan(
        target_reduction=target_days,
        achieved_reduction=total_overlap,
        crash_activities=[],
        fast_track_options=selected_options,
        total_additional_cost=total_risk_cost,
        new_project_duration=new_duration,
        risk_assessment=f"{risk_text} - potential rework if predecessor changes"
    )

def optimize_compression(self, target_days: int,
                        max_budget: float,
                        max_risk: str = "medium") -> CompressionPlan:
    """Find optimal combination of crashing and fast-tracking."""
    # Try crash-only
    crash_plan = self.crash_schedule(target_days, max_budget)

    if crash_plan.achieved_reduction >= target_days:
        return crash_plan

    # Need additional fast-tracking
    remaining_days = target_days - crash_plan.achieved_reduction
    remaining_budget = max_budget - crash_plan.total_additional_cost

    fast_track_plan = self.fast_track_schedule(remaining_days, max_risk)

    # Combine plans
    total_reduction = crash_plan.achieved_reduction + fast_track_plan.achieved_reduction
    total_cost = crash_plan.total_additional_cost + fast_track_plan.total_additional_cost

    return CompressionPlan(
        target_reduction=target_days,
        achieved_reduction=total_reduction,
        crash_activities=crash_plan.crash_activities,
        fast_track_options=fast_track_plan.fast_track_options,
        total_additional_cost=total_cost,
        new_project_duration=self.project_duration - total_reduction,
        risk_assessment="Combined approach - balance of cost and risk"
    )

def generate_cost_curve(self, max_compression: int) -> List[Dict]:
    """Generate time-cost tradeoff curve."""
    curve = []
    self.calculate_project_duration()
    original_duration = self.project_duration

    # Reset all activities to normal
    for act in self.activities.values():
        act.current_duration = act.normal_duration

    base_cost = sum(act.normal_cost for act in self.activities.values())

    curve.append({
        'duration': original_duration,
        'cost': base_cost,
        'compression': 0
    })

    for days in range(1, max_compression + 1):
        # Reset and crash by 'days'
        for act in self.activities.values():
            act.current_duration = act.normal_duration

        plan = self.crash_schedule(days)

        if plan.achieved_reduction < days:
            break

        curve.append({
            'duration': plan.new_project_duration,
            'cost': base_cost + plan.total_additional_cost,
            'compression': days
        })

    return curve

def generate_compression_report(self, plan: CompressionPlan) -> str:
    """Generate compression analysis report."""
    lines = [
        "# Schedule Compression Report",
        "",
        f"**Target Reduction:** {plan.target_reduction} days",
        f"**Achieved Reduction:** {plan.achieved_reduction} days",
        f"**New Duration:** {plan.new_project_duration} days",
        f"**Additional Cost:** ${plan.total_additional_cost:,.0f}",
        "",
        f"## Risk Assessment",
        f"{plan.risk_assessment}",
        ""
    ]

    if plan.crash_activities:
        lines.append("## Crashed Activities")
        lines.append("")
        lines.append("| Activity | Days Crashed | Cost Impact |")
        lines.append("|----------|--------------|-------------|")
        for act_id, days in plan.crash_activities:
            act = self.activities[act_id]
            cost = days * act.crash_slope
            lines.append(f"| {act.name} | {days} | ${cost:,.0f} |")
        lines.append("")

    if plan.fast_track_options:
        lines.append("## Fast-Tracked Activities")
        lines.append("")
        for opt in plan.fast_track_options:
            lines.append(f"- **{opt.activity1_id} → {opt.activity2_id}**: {opt.overlap_days} days overlap")
            lines.append(f"  - Risk: {opt.risk_level} - {opt.risk_description}")
        lines.append("")

    return "\n".join(lines)

Quick Start

Initialize compressor

compressor = ScheduleCompressor()

Add activities with crash data

compressor.add_activity( "A", "Foundation", normal_duration=20, crash_duration=15, normal_cost=100000, crash_cost=130000, is_critical=True ) compressor.add_activity( "B", "Steel Erection", normal_duration=30, crash_duration=22, normal_cost=200000, crash_cost=260000, predecessors=["A"], is_critical=True ) compressor.add_activity( "C", "MEP Rough-in", normal_duration=25, crash_duration=20, normal_cost=150000, crash_cost=180000, predecessors=["B"], is_critical=True )

Add fast-track options

compressor.add_fast_track_option( "A", "B", overlap_days=5, risk_level="medium", risk_description="Steel may need rework if foundation changes", rework_probability=0.15, potential_rework_cost=30000 )

Analyze crash options

print("Crash Options (sorted by cost/day):") for opt in compressor.analyze_crash_options(): print(f" {opt['activity_name']}: ${opt['crash_slope']:.0f}/day, max {opt['max_days']} days")

Compress schedule by 15 days

plan = compressor.optimize_compression( target_days=15, max_budget=80000, max_risk="medium" )

print(compressor.generate_compression_report(plan))

Generate cost curve

curve = compressor.generate_cost_curve(20) for point in curve: print(f"Duration: {point['duration']}d, Cost: ${point['cost']:,.0f}")

Requirements

pip install (no external dependencies)

Source Transparency

This detail page is rendered from real SKILL.md content. Trust labels are metadata-based hints, not a safety guarantee.

Related Skills

Related by shared tags or category signals.

Automation

drawing-analyzer

No summary provided by upstream source.

Repository SourceNeeds Review
Automation

dwg-to-excel

No summary provided by upstream source.

Repository SourceNeeds Review
Automation

cost-estimation-resource

No summary provided by upstream source.

Repository SourceNeeds Review
Automation

daily-progress-report

No summary provided by upstream source.

Repository SourceNeeds Review