Critical Path Analyzer

Business Case

Problem Statement

Schedule management requires understanding:

  • Which activities are critical?

  • How much float exists?

  • What delays impact completion?

  • Where to focus resources?

Solution

Analyze schedule network to identify critical path, calculate float, and provide actionable schedule insights.

Technical Implementation

import pandas as pd import numpy as np from typing import Dict, Any, List, Optional, Set from dataclasses import dataclass, field from datetime import date, timedelta from enum import Enum from collections import defaultdict

class ActivityStatus(Enum): NOT_STARTED = "not_started" IN_PROGRESS = "in_progress" COMPLETED = "completed" DELAYED = "delayed"

@dataclass class Activity: activity_id: str name: str duration: int # days predecessors: List[str] early_start: int = 0 early_finish: int = 0 late_start: int = 0 late_finish: int = 0 total_float: int = 0 free_float: int = 0 is_critical: bool = False status: ActivityStatus = ActivityStatus.NOT_STARTED percent_complete: float = 0 actual_start: Optional[date] = None actual_finish: Optional[date] = None

@dataclass class CriticalPathResult: critical_path: List[str] project_duration: int activities: Dict[str, Activity] near_critical: List[str] # Float < 5 days total_float_days: int

class CriticalPathAnalyzer: """Analyze project critical path."""

NEAR_CRITICAL_THRESHOLD = 5  # days

def __init__(self, project_start: date):
    self.project_start = project_start
    self.activities: Dict[str, Activity] = {}

def add_activity(self,
                 activity_id: str,
                 name: str,
                 duration: int,
                 predecessors: List[str] = None):
    """Add activity to network."""

    self.activities[activity_id] = Activity(
        activity_id=activity_id,
        name=name,
        duration=duration,
        predecessors=predecessors or []
    )

def import_from_dataframe(self, df: pd.DataFrame):
    """Import activities from DataFrame."""
    for _, row in df.iterrows():
        preds = row.get('predecessors', '')
        if pd.isna(preds):
            pred_list = []
        else:
            pred_list = [p.strip() for p in str(preds).split(',') if p.strip()]

        self.add_activity(
            activity_id=str(row['activity_id']),
            name=row['name'],
            duration=int(row['duration']),
            predecessors=pred_list
        )

def _forward_pass(self):
    """Calculate early start and early finish (forward pass)."""

    # Topological sort
    sorted_activities = self._topological_sort()

    for activity_id in sorted_activities:
        activity = self.activities[activity_id]

        # Early start = max(early finish of all predecessors)
        if not activity.predecessors:
            activity.early_start = 0
        else:
            activity.early_start = max(
                self.activities[pred].early_finish
                for pred in activity.predecessors
                if pred in self.activities
            )

        activity.early_finish = activity.early_start + activity.duration

def _backward_pass(self):
    """Calculate late start and late finish (backward pass)."""

    # Find project duration
    project_duration = max(a.early_finish for a in self.activities.values())

    # Build successors map
    successors = defaultdict(list)
    for activity_id, activity in self.activities.items():
        for pred in activity.predecessors:
            if pred in self.activities:
                successors[pred].append(activity_id)

    # Reverse topological order
    sorted_activities = self._topological_sort()[::-1]

    for activity_id in sorted_activities:
        activity = self.activities[activity_id]

        # Late finish = min(late start of all successors)
        if activity_id not in successors or not successors[activity_id]:
            activity.late_finish = project_duration
        else:
            activity.late_finish = min(
                self.activities[succ].late_start
                for succ in successors[activity_id]
            )

        activity.late_start = activity.late_finish - activity.duration

        # Calculate floats
        activity.total_float = activity.late_start - activity.early_start
        activity.is_critical = activity.total_float == 0

def _topological_sort(self) -> List[str]:
    """Topological sort of activities."""

    visited = set()
    result = []

    def visit(activity_id: str):
        if activity_id in visited:
            return
        visited.add(activity_id)

        activity = self.activities.get(activity_id)
        if activity:
            for pred in activity.predecessors:
                if pred in self.activities:
                    visit(pred)
            result.append(activity_id)

    for activity_id in self.activities:
        visit(activity_id)

    return result

def calculate_critical_path(self) -> CriticalPathResult:
    """Calculate critical path and all float values."""

    self._forward_pass()
    self._backward_pass()

    # Find critical path
    critical_activities = [
        a.activity_id for a in self.activities.values()
        if a.is_critical
    ]

    # Near-critical activities
    near_critical = [
        a.activity_id for a in self.activities.values()
        if 0 &#x3C; a.total_float &#x3C;= self.NEAR_CRITICAL_THRESHOLD
    ]

    project_duration = max(a.early_finish for a in self.activities.values())
    total_float = sum(a.total_float for a in self.activities.values())

    return CriticalPathResult(
        critical_path=critical_activities,
        project_duration=project_duration,
        activities=self.activities,
        near_critical=near_critical,
        total_float_days=total_float
    )

def get_schedule_dates(self) -> pd.DataFrame:
    """Get schedule with dates."""

    data = []
    for activity in self.activities.values():
        early_start_date = self.project_start + timedelta(days=activity.early_start)
        early_finish_date = self.project_start + timedelta(days=activity.early_finish)
        late_start_date = self.project_start + timedelta(days=activity.late_start)
        late_finish_date = self.project_start + timedelta(days=activity.late_finish)

        data.append({
            'Activity ID': activity.activity_id,
            'Name': activity.name,
            'Duration': activity.duration,
            'Early Start': early_start_date,
            'Early Finish': early_finish_date,
            'Late Start': late_start_date,
            'Late Finish': late_finish_date,
            'Total Float': activity.total_float,
            'Critical': 'Yes' if activity.is_critical else 'No'
        })

    return pd.DataFrame(data)

def analyze_delay_impact(self,
                         activity_id: str,
                         delay_days: int) -> Dict[str, Any]:
    """Analyze impact of delay on project."""

    activity = self.activities.get(activity_id)
    if not activity:
        return {}

    absorbed_by_float = min(delay_days, activity.total_float)
    project_delay = max(0, delay_days - activity.total_float)

    # Find affected activities
    affected = []
    if project_delay > 0:
        # Activities that could be affected (successors)
        for a in self.activities.values():
            if activity_id in a.predecessors:
                affected.append(a.activity_id)

    return {
        'activity': activity_id,
        'delay_days': delay_days,
        'available_float': activity.total_float,
        'absorbed_by_float': absorbed_by_float,
        'project_delay': project_delay,
        'affected_activities': affected,
        'is_critical_delay': project_delay > 0
    }

def suggest_acceleration(self,
                         target_reduction: int) -> List[Dict[str, Any]]:
    """Suggest activities to accelerate to meet target."""

    result = self.calculate_critical_path()
    suggestions = []

    # Focus on critical activities
    for activity_id in result.critical_path:
        activity = self.activities[activity_id]

        # Assume can reduce by 20% max
        max_reduction = int(activity.duration * 0.2)

        if max_reduction > 0:
            suggestions.append({
                'activity': activity_id,
                'name': activity.name,
                'current_duration': activity.duration,
                'max_reduction': max_reduction,
                'reason': 'Critical path activity'
            })

    # Sort by potential impact
    return sorted(suggestions, key=lambda x: x['max_reduction'], reverse=True)

def export_analysis(self, output_path: str) -> str:
    """Export analysis to Excel."""

    result = self.calculate_critical_path()

    with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
        # Summary
        summary_df = pd.DataFrame([{
            'Project Start': self.project_start,
            'Project Duration': result.project_duration,
            'Project Finish': self.project_start + timedelta(days=result.project_duration),
            'Critical Activities': len(result.critical_path),
            'Near-Critical Activities': len(result.near_critical),
            'Total Float (days)': result.total_float_days
        }])
        summary_df.to_excel(writer, sheet_name='Summary', index=False)

        # Schedule
        schedule_df = self.get_schedule_dates()
        schedule_df.to_excel(writer, sheet_name='Schedule', index=False)

        # Critical Path
        critical_df = pd.DataFrame([
            {
                'Activity': a_id,
                'Name': self.activities[a_id].name,
                'Duration': self.activities[a_id].duration
            }
            for a_id in result.critical_path
        ])
        critical_df.to_excel(writer, sheet_name='Critical Path', index=False)

    return output_path

Quick Start

from datetime import date

Initialize analyzer

analyzer = CriticalPathAnalyzer(project_start=date(2024, 6, 1))

Add activities

analyzer.add_activity("A", "Site Preparation", 10, []) analyzer.add_activity("B", "Foundation Excavation", 15, ["A"]) analyzer.add_activity("C", "Foundation Concrete", 20, ["B"]) analyzer.add_activity("D", "Structural Steel", 30, ["C"]) analyzer.add_activity("E", "MEP Rough-in", 25, ["C"]) analyzer.add_activity("F", "Exterior Walls", 20, ["D"]) analyzer.add_activity("G", "Interior Finish", 15, ["E", "F"])

Calculate critical path

result = analyzer.calculate_critical_path()

print(f"Project Duration: {result.project_duration} days") print(f"Critical Path: {result.critical_path}")

Common Use Cases

  1. Analyze Delay Impact

impact = analyzer.analyze_delay_impact("C", delay_days=5) print(f"Project Delay: {impact['project_delay']} days")

  1. Get Schedule Dates

schedule = analyzer.get_schedule_dates() print(schedule[['Activity ID', 'Early Start', 'Late Finish', 'Total Float']])

  1. Acceleration Suggestions

suggestions = analyzer.suggest_acceleration(target_reduction=10) for s in suggestions: print(f"{s['activity']}: can reduce {s['max_reduction']} days")

Resources

  • DDC Book: Chapter 4.2 - Schedule Analysis

Source Transparency

This detail page is rendered from real SKILL.md content. Trust labels are metadata-based hints, not a safety guarantee.

Related Skills

Related by shared tags or category signals.

Automation

cad-to-data

No summary provided by upstream source.

Repository SourceNeeds Review
Automation

drawing-analyzer

No summary provided by upstream source.

Repository SourceNeeds Review
Automation

dwg-to-excel

No summary provided by upstream source.

Repository SourceNeeds Review
Automation

cost-estimation-resource

No summary provided by upstream source.

Repository SourceNeeds Review